Our completed drinking water project consists of works such as totally 24.404 meter CTP and steel pipe in 900 mm diameter, 9.400 meter transmission line made of steel pipe, 2 units of 50 m² and 1 unit of 200 m² tanks, elevation centre with 2 groups, drainage system, vane chamber, emptying and vacuum lifter.
EMPLOYER
İLLER BANKASI GENEL MÜDÜRLÜĞÜ /ANKARA